Jharkhand State Electricity Board

 

FINANCIAL PROGRESS OF APDRP WORKS:  (As on March'08)

Sl. No.

Name of Circle

Scheme Provision

Cumulative Progress

%Progress

1

Ranchi Circle

114.19

83.41

73.04 %

2

Dumka Circle

63.61

34.34

53.99 %

3

Hazaribagh Circle

96.68

12.24

12.66 %

4

Jamshedpur & Ghatsila town

55.26

42.92

77.67 %

5

Dhanbad town

49.50

37.14

75.03 %

6

Deoghar town

9.32

16.17

173.5 %

7

Katras, Chas & Jharia Town

24.07

1.02

4.24 %

8

Daltonganj, Latehar & Garhwa Town

32.20

0.60

1.86 %

 

Total

444.83

241.38

54.27 %

Work Status of APDRP under 10th Plan

Description

Unit

Total targeted work

Work Completed

% Work Completed

Erection of New 33 kV Line

km

353.19

133.58

37.82%

Renovation of Existing 33 kV Line

km

461.79

83.26

18.03%

Erection of New 11 kV Line

km

601.4

95.21

15.83%

Renovation of Existing11 kV Line

km

1259.82

566.84

44.99%

Erection of New LT Line

km

593.3

60.24

10.15%

Renovation of Existing LT Line

km

1311.45

496.75

37.88%

Installation of New 33/11 kV PSS

Nos

7

2

28.57%

Renovation of Existing 33/11 kV PSS

Nos

53

3

5.66%

Installation of New DSS

Nos

3778

816

21.60%

Renovation of Existing DSS

Nos

4721

1509

31.96%

 

 

 

 

 

 

 