Status of Rajiv Gandhi Gramin Vidutikaran Yojna to be implemented by NTPC

Formal Sanction of the Scheme for the District accorded by REC

Sl. No.

District

Agency

Project Cost (In Crore Rs.)

Date of award of Work

1

Deoghar

M/s NTPC

96.99

March’ 07

2

Jamtara

M/s NTPC

84.18

May’ 07

3

Dumka

M/s NTPC

193.57

06.06.08

4

Godda

M/s NTPC

120.46

06.06.08

5

Ranchi

M/s NTPC

BID opened

on 02.06.08

6

Lohardaga

M/s NTPC

56.93

BID open on 04.06.08

7

Sahebganj

M/s NTPC

169.07

BID open on 20.06.08

8

Pakur

M/s NTPC

118.35

BID open on 24.06.08

RURAL ELECTRIFICATION DETAILS :

   

Total Electrified Villages :

Click here

RGGVY-JSEB as on 08-08-08:

Click here

RGGVY-DVC as on 08-08-08:

Click here

RGGVY-NTPC as on 08-08-08:

Click here

Agencywise Target and Achievement upto 08-08-08(JSEB)

Click here

Monthwise BPL progress Graph(JSEB)

Click here